KOKKINOTRIMITHIA

RES hosting capacity 39.84 MW
Available today 0.00 MW Saturated
Substation upgrade 2033 +48.5 MW (N-1) ΔΠΑΣΜ draft, under consultation

DSO priority list

3 of the 21 applications meet the maturity criteria and are in the priority line.

Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026

Applications RES MW Batteries MW / MWh
In line 3 1.65 3.5 / 14
All 21 66.071 72.5 / 225

In the priority line

Score up to 100: the higher, the further ahead.
Score Applicant RES MW Battery MW Battery MWh Application
100 BIOLAND PROJECT 44 LTD 3.5 14 498005548
35 BIOLAND PROJECT 86 LTD 1.5 400490147
35 ILLUSTRIS INVESTMENTS LTD 0.15 498000155
The 18 applications outside the line
Applicant RES MW Battery MW Battery MWh Application
Private individual 0.85 498000232
ΑΡΧΗ ΗΛΕΚΤΡΙΣΜΟΥ ΚΥΠΡΟΥ 3.1 498000749
ΑΡΧΗ ΗΛΕΚΤΡΙΣΜΟΥ ΚΥΠΡΟΥ 5.2 498000927
Private individual 0.15 498001446
Private individual 0.15 498001447
P&CK SOLAR LTD 0.131 498001933
AGM SOLAR POWER LTD 8 5 10 498002141
AGM SOLAR POWER LTD 8 5 10 498002142
AGM SOLAR POWER LTD 8 5 10 498002143
AGM SOLAR POWER LTD 8 5 10 498002145
AGM LIGHTPOWER LTD 5 5 6 498002153
AGM LIGHTPOWER LTD 5 3 6 498002154
AGM LIGHTPOWER LTD 8 5 10 498002155
SOLIGHT ELECTRICITY COMPANY LTD 2.14 1 4.5 498004763
RES ZEUS ELECTRICITY COMPANY LTD 2.7 1 4.5 498004764
GREENLOOP LIMITED 10 40 498005684
GREENLOOP LIMITED 12 50 498005695
GREENLOOP LIMITED 12 50 498005697

The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».

DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026

Sources: DSD, data of 2 Nov 2026 · DSMK, ΔΠΑΣΜ 2026-2035. The upgrade’s «+MW (N-1)» is our calculation of firm capacity, not a RES hosting capacity. It is not a connection approval or investment advice.