TEMBRIA

RES hosting capacity 25.72 MW
Available today 0.00 MW Saturated
Substation upgrade 2029 ΔΠΑΣΜ draft, under consultation

DSO priority list

5 of the 10 applications meet the maturity criteria and are in the priority line.

Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026

Applications RES MW Batteries MW / MWh
In line 5 0 35.99 / 115.22
All 10 15.564 39.24 / 121.72

In the priority line

Score up to 100: the higher, the further ahead.
Score Applicant RES MW Battery MW Battery MWh Application
100 ARMOLIA INVESTMENTS LTD 5 10.11 498004511
100 ΗΛΙΟΜΟΡΦΟΝ 1 ΛΤΔ 5 10.11 498004512
100 SANTIAM INVESTMENT I LTD 6.42 25 498005263
100 SANTIAM INVESTMENT I LTD 7.57 25 498005264
35 HELLENIQ RENEWABLES CYPRUS AGIA VARVARA LTD 12 45 ΔΣΜΚ(320.7.20)
The 5 applications outside the line
Applicant RES MW Battery MW Battery MWh Application
SOLEK CYPRUS SERVICES LTD 2.2 400458772
DENSOL R.LIMITED 1.15 498000374
HELLENIQ RENEWABLES CYPRUS AGIA VARVARA LTD 2.919 0.45 0.9 498003507
HELLENIQ RENEWABLES CYPRUS AGIA VARVARA LTD 1.995 0.3 0.6 498003509
CARCALINA LTD 7.3 2.5 5 498004083

The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».

DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026

Sources: DSD, data of 2 Nov 2026 · DSMK, ΔΠΑΣΜ 2026-2035. The upgrade’s «+MW (N-1)» is our calculation of firm capacity, not a RES hosting capacity. It is not a connection approval or investment advice.