PSEVDAS

Psevdas, Alexigros and Orites belong to DSMK and are shown as a separate class, not alongside EAC’s 52 substations.

RES hosting capacity 0.00 MW
Available today 0.00 MW Saturated
Substation upgrade 2028 +80 MW (N-1) ΔΠΑΣΜ draft, under consultation

DSO priority list

Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026

Applications RES MW Batteries MW / MWh
In line 0 0 0 / 0
All 0 0 0 / 0

The DSO lists no applications for this substation in this list.

The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».

DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026

Sources: DSD, data of 2 Nov 2026 · DSMK, ΔΠΑΣΜ 2026-2035. The upgrade’s «+MW (N-1)» is our calculation of firm capacity, not a RES hosting capacity. It is not a connection approval or investment advice.