POLEMIDHIA 132kV
RES hosting capacity 47.82 MW
Available today 15.94 MW
Substation upgrade 2034 +40 MW (N-1) ΔΠΑΣΜ draft, under consultation
DSO priority list
The one application meets the maturity criteria and is in the priority line.
Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026
| Applications | RES MW | Batteries MW / MWh | |
|---|---|---|---|
| In line | 1 | 0.62 | 0 / 0 |
| All | 1 | 0.62 | 0 / 0 |
In the priority line
| Score | Applicant | RES MW | Battery MW | Battery MWh | Application |
|---|---|---|---|---|---|
| 65 | BIOLAND PROJECT 62 LTD | 0.62 | 498003211 |
The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».
DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026