PAPACOSTAS

RES hosting capacity 69.28 MW
Available today 55.08 MW
Substation upgrade No year published

DSO priority list

All 3 applications meet the maturity criteria and are in the priority line.

Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026

Applications RES MW Batteries MW / MWh
In line 3 2.656 1.25 / 5.664
All 3 2.656 1.25 / 5.664

In the priority line

Score up to 100: the higher, the further ahead.
Score Applicant RES MW Battery MW Battery MWh Application
100 LECCINO SOLAR LTD 1.416 1.25 5.664 498005670
65 ΑΝΤΩΝΑΚΗΣ ΠΟΓΙΑΤΖΗΣ ΛΤΔ 0.04 498004628
65 QUINARA LTD 1.2 498005603

The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».

DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026

Sources: DSD, data of 2 Nov 2026 · DSMK, ΔΠΑΣΜ 2026-2035. The upgrade’s «+MW (N-1)» is our calculation of firm capacity, not a RES hosting capacity. It is not a connection approval or investment advice.

Want a professional check on a parcel served by this substation?

Parcel check →
Back to the map