Skip to content

LAKATAMIA

RES hosting capacity 50.42 MW
Available today 0.00 MW Saturated
Substation upgrade No year published

DSO priority list

7 of the 21 applications meet the maturity criteria and are in the priority line.

Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026

Applications RES MW Batteries MW / MWh
In line 7 0.467 10.97 / 38.615
All 21 25.763 43.87 / 157.615

In the priority line

Score up to 100: the higher, the further ahead.
Score Applicant RES MW Battery MW Battery MWh Application
100 ERGO ENERGY PV PARKS LTD 2.47 5.015 498005344
100 HAFFNEVE HOLDING LIMITED 3 12 498005445
100 BIOLAND PROJECT 19 LTD 2 8 498005547
100 BIOLAND PROJECT 29 LTD 0.9 3.6 498005581
100 METTAS ECO ENERGY LIMITED 2.6 10 498005693
65 MIMAP CONSTRUCTION LTD 0.12 498003477
30 MIMAP CONSTRUCTION LTD 0.347 498004088
The 14 applications outside the line
Applicant RES MW Battery MW Battery MWh Application
ΑΡΧΗ ΗΛΕΚΤΡΙΣΜΟΥ ΚΥΠΡΟΥ 2.1 498000748
ARISTOKLIA SOLAR LTD 0.495 498001382
S S H SOLAR ENERGY LTD 4 498001692
S S H SOLAR ENERGY LTD 1.8 498001806
4F SOLAR ENERGY LTD 1.506 1.5 3 498002934
PETROLINA ENERGY LTD 1.5 498003045
HELLENIQ RENEWABLES CYPRUS 1.37 1 4 498003662
NAT ENERGY LIMITED 0.591 498003960
NAT ENERGY LIMITED 0.98 498003961
Private individual 4.004 4 24 498004061
CAPERLIR INVESTMENTS LTD 0.95 0.4 2 498005059
RISANTHI LTD 6 6 6 498005197
ELOADS ENERGIES STORAGE LTD 8 30 498005564
GREENLOOP LIMITED 12 50 498005683

The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».

DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026

Sources: DSD, data of 2 Nov 2026 · DSMK, ΔΠΑΣΜ 2026-2035. The upgrade’s «+MW (N-1)» is our calculation of firm capacity, not a RES hosting capacity. It is not a connection approval or investment advice.

Want a professional check on a parcel served by this substation?