INTERNATIONAL AIRPORT (GIS)
RES hosting capacity 85.60 MW
Available today 43.48 MW
Substation upgrade No year published
DSO priority list
All 4 applications meet the maturity criteria and are in the priority line.
Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026
| Applications | RES MW | Batteries MW / MWh | |
|---|---|---|---|
| In line | 4 | 0 | 19.302 / 46 |
| All | 4 | 0 | 19.302 / 46 |
In the priority line
| Score | Applicant | RES MW | Battery MW | Battery MWh | Application |
|---|---|---|---|---|---|
| 100 | HAFFNEVE HOLDING LTD | 4.672 | 12 | 498005389 | |
| 100 | HAFFNEVE HOLDING LTD | 6.1 | 12 | 498005393 | |
| 100 | HAFFNEVE HOLDING LTD | 4.93 | 12 | 498005394 | |
| 100 | HAFFNEVE HOLDING LTD | 3.6 | 10 | 498005400 |
The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».
DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026