AYIOS ATHANASIOS
RES hosting capacity 49.79 MW
Available today 28.83 MW
Substation upgrade 2035 +40 MW (N-1) ΔΠΑΣΜ draft, under consultation
DSO priority list
The one application does not meet the maturity criteria yet, so it is not in the line.
Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026
| Applications | RES MW | Batteries MW / MWh | |
|---|---|---|---|
| In line | 0 | 0 | 0 / 0 |
| All | 1 | 0.63 | 0.63 / 2.52 |
The 1 application outside the line
| Applicant | RES MW | Battery MW | Battery MWh | Application |
|---|---|---|---|---|
| DOMOPLEX LTD | 0.63 | 0.63 | 2.52 | 498005630 |
The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».
DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026