AY.PHYLA
RES hosting capacity 66.32 MW
Available today 39.06 MW
Substation upgrade 2027 +20 MW (N-1) ΔΠΑΣΜ draft, under consultation
DSO priority list
None of the 2 applications meets the maturity criteria yet, so none is in the line.
Preliminary list 15/10/2026 · objections until 25/10/2026 · final ranking 1/11/2026
| Applications | RES MW | Batteries MW / MWh | |
|---|---|---|---|
| In line | 0 | 0 | 0 / 0 |
| All | 2 | 6.2 | 4.7 / 18.8 |
The 2 applications outside the line
| Applicant | RES MW | Battery MW | Battery MWh | Application |
|---|---|---|---|---|
| HELLENIQ RENEWABLES CY.PACHNA LTD | 3 | 1.5 | 6 | 498003568 |
| BP-S 135 LTD | 3.2 | 3.2 | 12.8 | 498005501 |
The line does not bind the DSO to issue connection terms. It leaves out projects already holding terms or connected. Private individuals show as «Private individual».
DSO (EAC), Information Bulletin No. 05/2026 · 15/10/2026